10                                    Landfill Gas Hazard

10.1                              Introduction

10.1.1.1                  This section identifies the hazards that are likely to be generated from the WENT Landfill and the proposed WENT Landfill Extension, during the construction and operation phases of this Project and evaluates the associated risk.  Mitigation measures and good site practices are recommended with reference to the EPD guidelines.

10.2                              Environmental Legislation, Policies, Plans, Standards and Criteria

10.2.1.1                  Environmental Protection Department (EPD) has issued two guidance notes regarding landfill gas hazard assessment, namely ProPECC PN 3/96 - Landfill Gas Hazard Assessment for Development Adjacent to Landfill and EPD/TR8/97 - Landfill Gas Hazard Assessment Guidance Note.  These two guidance notes set out the conditions under which a landfill gas hazard assessment should be carried out and provide guidance on undertaking a landfill gas hazard assessment.  The guidance notes recommended that in general, assessment of landfill gas hazard is required for proposed developments that lie within the 250m Consultation Zone around a landfill.  Figure 10.1 shows the details of the planned facilities of STF that will be located within the consultation zone of the existing WENT Landfill.

10.2.1.2                  Since the Project Site in the eastern part of the Ash Lagoon falls within the 250m Consultation Zone of WENT Landfill, a qualitative landfill gas hazard assessment addressing the landfill gas hazards and recommending the mitigation measures is undertaken for the Project.

10.3                              History and General Description of the WENT Landfill

10.3.1.1                  WENT Landfill is an 110ha Landfill, which was commissioned in 1993, receiving waste from the West East New Territories by road as well as West Kowloon, North Lantau and Island East Transfer Stations, Island West Transfer Station, Outlying Island Transfer Stations by barge.  Its operation life is about 25 years and its aftercare period after the completion of operation is 30 years.

10.3.1.2                  The WENT landfill is designed in a “Confined and Contained” approach.  Comprehensive landfill gas and leachate collection systems were installed and operated.  Also, there is a protective lining system to stop any migration of landfill gas and leachate which forms a barrier on the pathway to nearby development.  Periodic monitoring exercise is being conducted to ensure that landfill gas and leachate are properly collected and treated.

10.3.1.3                  There is a proposed project on extensions of the existing WENT Landfill.  As shown in Figure 10.2[1], the proposed extension work of WENT Landfill will be divided into 6 phases covering total tipping volume of 81Mm3.  The time line of the proposed extension works is shown below.

Work

Construction Year

Operation Year

Phase 1

2016

2018

Phase 2

2017

2019

Phase 3

2018

2020

Phase 4

2020

2022

Phase 5

2021

2023

Phase 6

2022

2024

 

10.4                              Potential Landfill Gas Hazards

10.4.1.1                  The typical composition of landfill gas is about 60% volume of methane and 40% volume of carbon dioxide, although these percentages can vary widely depending on the site conditions.  Also present are trace quantities of hydrogen sulphide, nitrogen and gaseous hydrocarbons such as hexane, octane and heptane.

10.4.1.2                  Landfill gas migration can be a dangerous hazard because of its combustible and in some cases explosive nature of methane; and the asphyxiant nature of carbon dioxide.

10.4.1.3                  Landfill gas has the potential to cause fire, explosion or asphyxiation if it migrates into and accumulates in confined space such as building basements, underground car parks, lift shafts, pumping stations, and maintenance chambers.  For the same reasons, temporary structures such as site huts and any other unventilated enclosures erected during construction stage are also exposed to landfill gas hazards.  Underground services, such as sewer drains, storm drains and service ducts, may also be susceptible to the potential hazards as they act as pathways for landfill gas.  Besides, any faults present in geological formation also act as pathways for landfill gas.

10.4.1.4                  As shown in Figure 10.1, part of the STF site (including site of the administration building & laboratory, maintenance workshop, desalination plant, seawater pumping station & storage tank) falls within the 250m Consultation Zone of existing WENT Landfill.  Further, as illustrated in Figure 10.2, all parts of the STF site would fall within the 250m Consultation Zone of the proposed WENT Landfill extension and will be affected by the proposed WENT Landfill extension.  The overall risk level of landfill gas hazard posed by WENT Landfill and its proposed extension to the proposed STF is assessed and demonstrated below as recommended in EPD/TR8/97 - Landfill Gas Hazard Assessment Guidance Note

10.5                              Landfill Gas Assessment Criteria and Methodology

10.5.1                        Landfill Gas Assessment Criteria

10.5.1.1                  In accordance with the Landfill Gas Hazard Assessment Guidance Note, the risk due to landfill gas may be evaluated based upon the following three criteria:

·                Source – location, nature and likely quantities/ concentrations of landfill gas which has the potential to affect the development;

·                Pathway – the ground and groundwater conditions, through which landfill gas must pass in order to reach the development; and

·                Target – elements of the development that are sensitive to the effects of landfill gas.

 

10.5.2                        Source

10.5.2.1                   The classification of the Source (ie the landfill) should be undertaken as follows:

Minor

Landfill sites at which gas controls have been installed and proven to be effective by comprehensive monitoring which has demonstrated that there is no migration of gas beyond the landfill boundary (or any specific control measures) and at which control of gas does not rely solely on an active gas extraction system or any other single control measure which is vulnerable to failure; or

Old landfill sites where the maximum concentration of methane within the waste, as measured at several locations across the landfill and on at least four occasions over a period of at least 3 months (preferably longer), is less than 5% by volume (v/v).

Medium

Landfill site at which some form of gas control has been installed (eg lined site or one where vents or barriers have been retrospectively installed) but where there are only limited monitoring data to demonstrate its efficacy to prevent migration of gas; or

Landfill site where comprehensive monitoring has demonstrated that there is no migration of gas beyond the landfill boundary but where the control of gas relies solely on an active gas extraction system or any other single control system which is vulnerable to failure.

Major

Recently filled landfill site at which there is little or no control to prevent migration of gas or at which the efficacy of the gas control measures has not been assessed; or

Any landfill site at which monitoring has demonstrated that there is significant migration of gas beyond the site boundary.

 

10.5.2.2                  The 'significance' of migration should be assessed by reference to the concentration, frequency and location at which gas is detected.  For guidance, it should be assumed that any concentration of methane or carbon dioxide greater than 5% v/v above background levels in any monitoring well outside the landfill's boundary indicates significant migration.  Lower concentrations may still be 'significant' if they are observed in more than one monitoring well, on several occasions or in monitoring wells located some distance from the site boundary.  In general, concentrations of greater than 1% v/v methane or 1.5% v/v carbon dioxide (above background levels in each case) indicate less than adequate control of the gas at source.

10.5.2.3                  In classifying the source term, account needs to be taken of the likelihood and probable effect of a failure of the gas controls.  Thus, if it has been demonstrated that there is no migration of gas and there is little danger of the gas controls failing (eg if these comprise solely of passive measures such as a liner) it can be assumed that the site represents a "Minor" Source.  Where there is no gas migration but this may be as a result of a single, "vulnerable" control measure (eg. an active extraction system with no warning of failure), the site should be regarded as a "Medium" or even a "Major" Source depending on the other factors (eg size of site and age of waste).

10.5.2.4                  Where the effectiveness of the gas controls has not been proven by off-site monitoring or if there is some doubt as to the adequacy of the monitoring, this should be taken into account when considering the impact of the control measures on the Source term.  Assessments should always err on the side of caution and, in general, if the effectiveness cannot be demonstrated, the assessment should be undertaken on the same basis as if the controls were not in place.

10.5.2.5                  The reliability of the monitoring, for determining the efficacy of the gas controls, needs to take account of the design, number and location of the monitoring points together with the frequency and duration over which monitoring has been undertaken.  Monitoring should have been undertaken under different weather conditions including, in particular, periods of low or falling atmospheric pressure.

10.5.3                        Pathway

10.5.3.1                  The broad classification of the Pathway should be undertaken as follows:

Very short / direct

Path length of less than 50m for unsaturated permeable strata and fissured rock or less than 100m for man-made conduits

Moderately short / direct

Path length of 50-100m for unsaturated permeable soil or fissured rock or 100-250m for man-made conduits

Long / indirect

Path length of 100-250m for unsaturated permeable soils and fissured rock

 

10.5.3.2                  In classifying the pathway, however, adjustment to the above general guidelines will often be required to take account of other factors which will affect the extent of gas migration including the following:

·                particular permeability of the soils;

·                spacing, tightness and direction of the fissures/joints;

·                topography;

·                depth and thickness of the medium through which the gas may migrate (which may be affected by groundwater level);

·                the nature of the strata over the potential pathway;

·                the number of different media involved; and

·                depth to groundwater table and flow patterns.

 

10.5.3.3                  Thus, although there may be permeable soil between the landfill site and a proposed development say 80m from the edge of the site, if the soil layer is very shallow and thin with its upper surface exposed to the atmosphere, then it will be appropriate to consider this as a long/indirect pathway.  This could of course alter if the land between the landfill site and the development was paved over or altered in some other way which reduced the potential for gas release.  Similarly, if the land is flat, the surface may be prone to waterlogging which will also effectively seal it at times of heavy rain.  In general, a conservative approach should be adopted and it should be assumed that any such permeable surface soils may become less permeable in the future.

10.5.3.4                  If it is known that a conduit (man-made or natural feature such as a fault plane) leads directly from the landfill to the development area, it should be regarded as a "direct/short" pathway even if it is longer than 100m.

10.5.4                        Target

10.5.4.1                  Different types of target may be broadly classified as follows:

High sensitivity

Buildings and structures with ground level or below ground rooms/voids or into which services enter directly from the ground and to which members of the general public have unrestricted access or which contain sources of ignition.

This would include any developments where there is a possibility of additional structures being erected directly on the ground on an ad hoc basis and thereby without due regard to the potential risks.

 

Medium sensitivity

Other buildings, structures or service voids where there is access only by authorised, well trained personnel, such as the staff of utility companies, who have been briefed on the potential hazards relating to landfill gas and the specific safety procedures to be followed.

Deep excavations.

 

Low sensitivity

Buildings/structures which are less prone to gas ingress by virtue of their design (such as those with a raised floor slab).

Shallow excavations.

Developments which involve essentially outdoor activities but where evolution of gas could pose potential problems.

 

10.5.4.2                  The classification of the above LFG sources, pathway and target are categorized.  Having determined into which categories of source, pathway and target the combination of landfill and development fall, a preliminary assessment of the overall risk may be made by reference to Table 10.1.  The potential implications associated with the various qualitative risk categories are summarized in Table 10.2.

Table 10.1          Classification of Risk Category

Source

Pathway

Target Sensitivity

Risk Category

Major

Very short/direct

High

Very high

Medium

high

Low

Medium

Moderately short/direct

High

High

Medium

Medium

Low

Low

Long/indirect

High

High

Medium

Medium

Low

Low

Medium

Very short/direct

High

High

Medium

Medium

Low

Low

Moderately short/direct

High

High

Medium

Medium

Low

Low

Long/indirect

High

Medium

Medium

Low

Low

Very low

Minor

Very short/direct

High

High

Medium

Medium

Low

Low

Moderately short/direct

High

Medium

Medium

Low

Low

Very low

Long/indirect

High

Medium

Medium

Low

Low

Very low

 

Table 10.2          Summary of General Categorization of Risk

Category

Level of Risk

Implication

A

Very high

The type of development being proposed is very undesirable and a less sensitive form of development should be considered. At the very least, extensive engineering measures, alarm systems and emergency action plans are likely to be required.

B

High

Significant engineering measures will be required to protect the planned development.

C

Medium

Engineering measures will be required to protect the proposed development.

D

Low

Some precautionary measures will be required to ensure that the planned development is safe.

E

Very low (insignificant)

The risk is so low that no precautionary measures are required.

 

10.5.4.3                  Five generic forms of protection will be used in mitigating the hazards to development.  These generic forms corresponding to the five risk levels are set out in Table 10.3.  The terms used in Table 10.3 are defined in Table 10.4.

 

Table 10.3          Generic Protection Measures for Planning Stage Categorization

Category

Generic Protection Measures

A

For the planned development active control of gas, supported by barriers and detection systems.  Another, less sensitive form of development should also be considered.

B

Active control of gas, including barriers and detection systems (1).

C

Use of “semi active” or enhanced passive controls.  Detection systems in some situations.

D

Passive control of gas only.

E

No precautionary measures required.

Note:

(1)       The gas protection measures required to allow the safe development of a Category A risk development will need to be more extensive than those for a Category B risk development.

 

Table 10.4          Definition of Control Terms

Term

Definition

Active control

Control of gas by mechanical means eg ventilation of spaces with air to dilute gas, or extraction of gas from the development site using fans or blowers.

'Semi active' control

Use of wind driven cowls and other devices which assist in the ventilation of gas but do not rely on electrically powered fans.

Passive control

 

Provision of barriers to the movement of gas eg membranes in floors or walls, or in trenches, coupled with high permeability vents such as no-fines gravel in trenches or voids/permeable layers below structures.

Detection systems

 

Electronic systems based upon, for example, catalytic oxidation or infra-red measurement principles, which can detect low concentrations of gas in the atmosphere and can be linked to alarms and/or telemetry systems.

 

10.6                              Assessment of Potential Risk

10.6.1                        Source

10.6.1.1                  The existing WENT Landfill is a large and operating landfill (i.e. a significant source of LFG) and it relies on an active extraction system for LFG management.  The gas control system has been proven to be effective by comprehensive monitoring which has demonstrated that there is no migration of gas beyond the landfill boundary with reference to the recent monitoring data (Appendix 10.1).  The Source of landfill gas at WENT Landfill is therefore categorized as MEDIUM.

10.6.1.2                  The proposed future WENT Landfill Extensions is a source to generate LFG during the operation and aftercare phases.  With the LFG control measures and utilization facilities in the future WENT Landfill Extensions, it is anticipated that the source of LFG will be properly controlled within the site similar to the operation of the existing WENT Landfill.  The source of LFG at the future landfill extension is therefore categorized as MEDIUM.

10.6.2                        Pathway

10.6.2.1                  The buildings which fall within the existing WENT Landfill consultation zone are located 100-250m from the landfill.  Besides, the presence of the nullah and the sloping seawall (built with a lot of rubble and aggregate) facing the nullah act as a passive venting system to stop LFG from further migrating to the STF site.  Although the upstream area of the nullah bed (south of the STF site, Figure 10.1 refers) could be exposed at the lowest tide, the majority of the nullah is still covered with water at most of the time.  In particular, the intertidal area (east of the STF site) has high water level.  Thus, this nullah will provide a form of protection to the STF site.

10.6.2.2                  According to the Hong Kong Geological Survey Map (Scale 1:20,000) on the solid and superficial geology of Tsing Shan (Castle Peak), the superficial geology of the STF was mainly “marine sand” with part of “undivided, mainly marine mud”.  The subsoil underneath the STF facilities would mainly be ash, which is very compact with low porosity.  Consider the nullah in between STF and WENT Landfill, the compact and low porosity subsoil, and a relatively high watertable, it is anticipated that the chance for LFG migrating to the STF site would be very remote.

10.6.2.3                  In view of more than 100m distance from existing WENT Landfill, the Pathway is classified as LONG/INDIRECT.

10.6.2.4                  For the proposed future WENT Landfill Extensions, the separation distance with the STF is anticipated to be shorter than 50m.  The Pathway of LFG at the future landfill extensions is classified as VERY SHORT/DIRECT.

10.6.3                        Target

10.6.3.1                  As shown in Figure 10.1, Administration Building & Laboratory, Maintenance Workshop, Desalination Plant, Seawater Pumping Station & Storage Tank would fall within the 250m Consultation Zone of the existing WENT Landfill.  It is anticipated that deep excavations for the construction of the building foundation and the construction of underground utilities would be involved during the construction phase of the proposed Project.  The risk level of deep excavations for Target Sensitivity is categorized as MEDIUM

10.6.3.2                  As shown in Figure 10.3A, underground structures such as culvert and basement of the Seawater Pumping Station are anticipated.  During operation phase, when the gas at these locations accumulate and mix with air, the resultant mixture may explode in the presence of an ignition source.  There is a risk of asphyxiation to persons using poorly ventilated enclosed spaces, where gas is accumulated.  However, access to the underground service voids will only allow authorized or well-trained personnel who have been briefed on the potential hazards relating to landfill gas and the specific safety procedures to be followed.  As such, the risk level for this Target Sensitivity is categorized as MEDIUM.

10.6.3.3                  Administrative Building & Laboratory and Maintenance Workshop are generally restricted to authorized personnel.  The risk level for this Target Sensitivity is therefore categorized as MEDIUM.

10.6.3.4                  The earliest operation phase of the proposed future WENT Landfill Extensions will commence in Year 2016 while the construction of STF would be completed by Year 2012.  As such, the future WENT Landfill Extensions will not affect the construction of STF. 

10.6.3.5                  However, all parts of the STF such as the incineration system would fall within the consultation zone of the future WENT Landfill Extensions.  As shown in Figure 10.3B, underground structures of the incineration system such as the sludge hopper and boiler water system are anticipated.  In view that access to the service voids will only allow authorized or well-trained personnel who have been briefed on the potential hazards relating to landfill gas and the specific safety procedures to be followed, the risk level for this Target Sensitivity is categorized as MEDIUM.

10.6.4                        Summary of Qualitative Source-Pathway-Target Analysis

10.6.4.1                  Based on the information above, source-pathway-target analysis have been undertaken and the Overall Risk Level for both construction and operation phases of the proposed Project associated with the existing WENT Landfill is Low while the risk level for the operation phase of the project associated with the proposed WENT Landfill Extension is Medium.  Source-Pathway-Target analysis have been undertaken and are summarized in Table 10.5.

Table 10.5          Qualitative Risk Assessment Matrix

Source

Pathway

Sensitivity Target

Risk

From Existing WENT Landfill:

(Medium Source)

More than 100m from the existing WENT Landfill

Nullah in between acting as passive barrier

(Long/Indirect Pathway)

Deep excavation during construction phase

(Medium Sensitivity Target)

Low

Operation & Maintenance of Seawater Pumping Station during operation phase

(Medium Sensitivity Target)

Low

Administration Building & Laboratory during operation phase

(Medium Sensitivity Target)

Low

From Proposed Future WENT Landfill Extensions

(Medium Source)

Less than 50m from the proposed future WENT Landfill Extensions:

(Very Short/ Direct Pathway)

Operation & Maintenance of Incineration System and Seawater Pumping Station during operation phases

(Medium Sensitivity Target)

Medium

Administration Building & Laboratory during operation phase

(Medium Sensitivity Target)

Medium

 

10.7                              Recommended Protection Measures

10.7.1                        Introduction

10.7.1.1                  According to Table 10.2, some precautionary measures are required to protect the proposed STF from the landfill gas risk due to the existing WENT Landfill and engineering measures will be required to protect the proposed STF from the proposed WENT Landfill extension.  According to Table 4.2 of the EPD’s Landfill Gas Hazard Assessment Guidance Note, the generic protection measures required include “use of ‘semi active’ or enhanced passive gas controls protection system in some situations”.  The recommended preventive measures are presented in the following sections.

10.7.2                        During Construction Phase

Appointment of Safety Officer

10.7.2.1                  A safety officer, trained in the use of gas detection equipment and landfill gas-related hazards, should be present on site throughout the groundworks phase.  The Safety Officer should be provide with an intrinsically safe portable instrument, which is appropriately calibrated and able to measure the following gases in the ranges indicated below:

Methane              0-100%           LEL and 1-100% v/v

Carbon dioxide    0-100%

Oxygen               0-21%

 

Safety Measures

10.7.2.2                  For staff who work in, or have responsibility for “at risk” area, such as all excavation workers, supervisors and engineers working within the Consultation Zone, should receive appropriate training on working in areas susceptible to landfill gas, fire and explosion hazards.

10.7.2.3                  An excavation procedure or code of practice to minimize landfill gas related risk should be devised and carried out.

10.7.2.4                  No worker should be allowed to work alone at any time in or near to any excavation.  At least one other worker should be available to assist with a rescue if needed.

10.7.2.5                  Smoking, naked flames and all other sources of ignition should be prohibited within 15m of any excavation or ground-level confined space.  “No smoking” and “No naked flame” notices should be posted prominently on the construction site and, if necessary, special areas should be designed for smoking.

10.7.2.6                  Welding, flame-cutting or other hot works should be confined to open areas at least 15m from any trench or excavation.

10.7.2.7                  Welding, flame-cutting or other hot works may be only be carried out in trenches or confined spaces when controlled by a “permit to work” procedure, properly authorized by the Safety Officer (or, in the case of small developments, other appropriately qualified person).

10.7.2.8                  The permit to work procedure should set down clearly the requirements for continuous monitoring for methane, carbon dioxide and oxygen throughout the period during which the hot works are in progress.  The procedure should also require the presence of an appropriately qualified person, in attendance outside the 'confined area', who should be responsible for reviewing the gas measurements as they are made, and who should have executive responsibility for suspending the work in the event of unacceptable or hazardous conditions.  Only those workers who are appropriately trained and fully aware of the potentially hazardous conditions which may arise should be permitted to carry out hot works in confined areas.

10.7.2.9                  Where there are any temporary site offices, or any other buildings located within the WENT Landfill Consultation Zone which have enclosed spaces with the capacity to accumulate landfill gas, then they should either be located in an area which has been proven to be free of landfill gas (by survey using portable gas detectors); or be raised clear of the ground by a minimum of 500mm.  This aims to create a clear void under the structure which is ventilated by natural air movement such that emission of gas from the ground are mixed and diluted by air.

10.7.2.10              Any electrical equipment, such as motors and extension cords, should be intrinsically safe.

10.7.2.11              During piping assembly or conduiting construction, all valves/seals should be closed immediately after installation.  As construction progresses, all valves/seals should be closed to prevent the migration of gases through the pipeline/conduit.  All piping/conduiting should be capped at the end of each working day.

10.7.2.12              During construction, adequate fire extinguishing equipment, fire-resistant clothing and breathing apparatus (BA) sets should be made available on site as shown in follow:-

·                Fire drills should be organized at not less than six monthly intervals; and

·                The contractor should formulate a health and safety policy, standards and instructions for site personnel to follow.

 

10.7.2.13              All personnel who work on the site and all visitors to the site should be made aware of the possibility of ignition of gas in the vicinity of excavations.  Safety notices (in Chinese and English) should be posted at prominent position around the site warning danger of the potential hazards.

10.7.2.14              For staff who work in, or have responsibility for ‘at risk’ areas, such as all excavation workers, supervisors and engineers working within the WENT Landfill Consultation Zone should receive appropriate training on working in areas susceptible to landfill gas, fire and explosion hazards.

10.7.2.15              Service runs within the Consultation Zone should be designated as “special routes” as shown in Figure 10.4A; utilities companies should be informed of this and precautionary measures should be implemented.  Precautionary measures should include ensuring that staff members are aware of the potential hazards of working in confined spaces such as manholes and service chambers, and that appropriate monitoring procedures are in place to prevent hazards due to asphyxiating atmospheres in confined spaces.  Detailed guidance on entry into confined spaces is given in Code of Practice on Safety and Health at Work in Confined Spaces (Labour Department, Hong Kong).

 

10.7.2.16              Periodically during ground-works construction within the 250m Consultation Zone, the works area should be monitored for methane, carbon dioxide and oxygen using appropriately calibrated portable gas detection equipment.  The monitoring frequency and areas to be monitored should be set down prior to commencement of ground-works either by the Safety Officer or an approved and appropriately qualified person.

Monitoring

10.7.2.17              Routine monitoring should be carried out in all excavations, manholes, chambers, relocation of monitoring wells and any other confined spaces that may have been created.  All measurements in excavations should be made with the extended monitoring tube located not more than 10 mm from the exposed ground surface.  Monitoring should be performed properly to make sure that the area is free of landfill gas before any man enters into the area.

10.7.2.18              For excavations deeper than 1m, measurements should be carried out:-

·                at the ground surface before excavation commences;

·                immediately before any worker enters the excavation;

·                at the beginning of each working day for the entire period the excavation remains open; and

·                periodically through out the working day whilst workers are in the excavation.

 

10.7.2.19              For excavations between 300mm and 1m deep, measurements should be carried out:

·                directly after the excavation has been completed; and

·                periodically whilst the excavation remains open

 

10.7.2.20              For excavations less than 300mm and 1m deep, monitoring may be omitted, at the discretion of the Safety Officer or other appropriately qualified person.

10.7.2.21              Depending on the results of the measurements, actions required will vary and should be set down by the Safety Officer or other appropriately qualified person.  As a minimum these should encompass those actions specified in Table 10.6.

 


Table 10.6          Actions in the Event of Landfill Gas Being Detected in Excavations/Confined Areas

Parameter

Measurement

Action

Oxygen

< 19 %

·          Ventilate to restore oxygen to > 19 %

 

< 18 %

·          Stop works

·          Evacuate personnel/prohibit entry

·          Increase ventilation to restore oxygen to > 19 %

Methane

> 10 % LEL (i.e. > 0.5 % by volume)

·          Prohibit hot works

·          Ventilate to restore methane to < 10% LEL

 

> 20 % LEL (i.e. > 1 % by volume)

·          Stop works

·          Evacuate personnel/prohibit entry

·          Increase ventilation to restore methane to < 10 % LEL

Carbon Dioxide

> 0.5 %

·          Ventilate to restore carbon dioxide to < 0.5%

> 1.5 %

·          Stop works

·          Evacuate personnel/prohibit entry

·          Increase ventilation to restore carbon dioxide to <0.5%

 

10.7.2.22              The hazards from landfill gas during the construction stage within the existing WENT Landfill Consultation Zone should be minimized by suitable precautionary measures recommended in Chapter 8 of the Landfill Gas Hazard Assessment Guidance Note.  A copy of which is enclosed in Appendix 10.2.  In the operation phase, if it is necessary to carry out construction works, landfill gas precautionary measures same as those recommended for the construction stage above should be followed.

10.7.3                        Design of Landfill Gas Protection Measures and other Protection Measures During Operation Phase

Gas Barrier

10.7.3.1                  The most common way of preventing gas from entering an area of ground is to set a “gas barrier” into the ground which is either keyed into low permeability strata or extends at least 1m below the lowest groundwater level.

10.7.3.2                  The presence of a gas barrier to the movement of gas may lead to a gradual build up of gas on the landfill side of the barrier if the gas migration pathway is covered by low permeability materials.  To relieve the potential build up of gas, it may be necessary to install additional measures for venting the gas such as trenches filled with no-fines, granular material, e.g. gravel, connected to venting pipes which will provide a preferential pathway for the release of gas to atmosphere.  An outline of a landfill gas cut-off barrier is shown in Figure 10.4B and a more detailed typical design of it is shown in Figure 10.4C.

10.7.3.3                  To cut off any landfill gas migration from the existing WENT landfill to STF, it is proposed that a landfill gas cut-off trench barrier be built along the boundary of the STF facility from the bank of the nullah to the boundary of the existing WENT Landfill consultation zone as shown in Figure 10.5.  In addition, in the proposed WENT Landfill extension project, a cut-off trench barrier will be built along the boundary between the STF and the proposed WENT Landfill Extension under the WENT Extension project.  This will cut off any gas migration to the STF from the WENT Landfill Extension.  The indicative location of the proposed cut-off trench barrier is shown in Figure 10.5.

10.7.3.4                  It is also recommended that several landfill gas monitoring wells be installed into the ground on the development side of the gas barrier.  These are used to measure the concentrations of methane and carbon dioxide within the ground and hence determine the effectiveness of the measures in preventing LFG migration. 

Building Protection Design Measures

10.7.3.5                  Passive control measures for buildings structures with ground level or below ground rooms / voids including the following could be considered in the detailed design if necessary:-

·                Gas-resistant polymeric membranes which can be incorporated into the floor or wall construction as a continuous sealed layer.  Membranes should be able to demonstrate low gas permeability and resistant to possible chemical attack and may incorporate aluminum wafers to improve performance;

·                Other building materials, e.g. dense well-compacted concrete or steel shuttering which provide a measure of resistance to gas permeation;

·                Creation of a clear void under the structure which is ventilated by natural structure and provides preferential pathways for release of gas;

·                Synthetic composite geotextile which provide a free-venting cellular structure and provide preferential pathways for release of gas; and

·                Passive control measures may be used in low and medium risk situations where gas emissions are expected to be at relatively low rates and concentrations and venting to atmosphere is unlikely to cause a hazard or nuisance due to the low concentration or high dilution which will occur. 

 

Design Measures for Sub-Surface Building Services

10.7.3.6                  As shown in Figure 10.4B to Figure 10.4C and Figure 10.6A to Figure 10.6C, generic protection measures for the sub-surface building services including the following are recommended:-

·                A gas barrier used to prevent movement of gas through services may form part of a more extensive barrier to prevent general mitigation towards the development.  The gas barrier may be made of clay (or clay-rich soils), bentonite or polymeric membranes (e.g. HDPE).  In the case of water pipes and sewers which are not always fully filled, water traps e.g. U-bends, should be provided to effectively seal off the conduit and prevent gas-phase transport; and

·                Vent pipes or gridded manhole covers may be used to avoid build-up of gas in underground utilities manholes.  Venting stacks may be built into inspection chambers or connected to collection pipes in high permeability drainage layers adjacent to gas barriers.  Under all circumstances, care should be taken when accessing any manhole chambers especially those which are not fitted with vents and necessary safety procedures must be followed. 

 

Guidance for Entry into Service Rooms / Voids, Manholes and Chambers

10.7.3.7                  During the operation phase, any service voids, manholes, chambers or culvert within the proposed site, which is large enough to permit access to personnel should be subject to entry safety procedures.  Works in confined spaces are controlled by the Factories and Industrial Undertakings (Confined Spaces) Regulation of the Factories and Industrial Undertakings Ordinance and the Safety Guide to Working in Confined Spaces should be followed to ensure compliance with the Regulation.

10.7.3.8                  In general, when work is being undertaken in confined spaces, sufficient approved resuscitation equipment, breathing apparatus and safety torches should be made available.  Persons involved in or supervising such work should be trained and practiced in the use of such equipment.  A permit-to-work system for entry into confined spaces should be developed by an appropriately qualified person and the system should be consistently employed.  The safety measures recommended in Chapter 8 of the Landfill Gas Hazard Assessment Guidance Note should also be strictly followed.

10.7.3.9                  All the access to confined spaces should be restricted only to authorized personnel who are aware of the landfill gas hazard.  No general public should be permitted or allowed to access the service voids, manholes, chambers or wells.

Landfill Gas Monitoring

10.7.3.10              Regular Monitoring of landfill gas should be done at the monitoring wells mentioned in Section 10.7.3.4 as well as at the underground service voids and manholes by the STF contractor.   Monitoring is required to verify the effectiveness and to ensure the continued performance of the implemented protection measures. 

10.7.3.11              As this Project is at the Preliminary Design Stage, a detailed design is not available yet.  When the detailed design of the Project is available, the Design-Build-Operate (DBO) contractor of the STF is required to undertake further landfill gas hazard assessment to take account of the more readily available detailed information to finalize the design of the landfill gas protection measures recommended in this report.  During the detailed design stage, a review of this preliminary qualitative risk assessment should be carried out and a detailed qualitative landfill gas risk assessment should be prepared.  The detailed qualitative landfill gas risk assessment together with the detailed design of gas protection measures should be submitted to EPD for vetting.

10.7.3.12              The design of the landfill gas precautionary measures to be adopted on-site should be performed by a competent professional person who has knowledge on LFG protection measures appointed by the DBO contractor of the STF.  The design should also be checked and certified by a qualified independent consultant.  The DBO contractor should ensure that the required protection measures are implemented and constructed in accordance with the design and a maintenance and monitoring programme should be established to ensure the continued performance of the implemented protection measures.  The above requirements should be included in the tender documents of the STF.

10.8                              Conclusions

10.8.1.1                  The landfill gas hazard assessment shows that the overall level of landfill gas risk posed by the existing WENT Landfill to the Project is low while the risk posed by the proposed WENT Landfill extension is medium.  Appropriate protective measures have been proposed to minimize the landfill gas risk for the proposed project site during construction phase and operation phase.  In particular, it is proposed that landfill gas barriers be built at the site boundary of this Project to cut off any landfill gas migration from WENT Landfill and its proposed extensions, and monitoring wells be installed into the ground for verifying the effectiveness of the above measures.

10.8.1.2                  Provided that all the recommended protection measures are implemented properly, the safety of the site workers and all personnel presence at the proposed Project site would be safeguarded and there would be no adverse impact anticipated on the feasibility of the proposed Project.

 

 

 



[1]  With reference to Agreement No. CE 43/2006 (EP) - West New Territories (WENT) Landfill Extensions – Feasibility Study, Draft Landfill Gas Hazard Assessment